Demolition Completed
January 1, 2023
Demolition of the properties 65 to 83 Raglan Avenue has been completed in December 2022. The site has been secured via fencing and on-site surveillance.
Environmental Readings
March 31, 2023
The former properties on the site were demolished back in November and December 2022. Since then, our environmental consultants have been on site doing environmental readings since January 2023. This includes drilling into the ground to take soil samples for a geotechnical and hydrogeological investigations. We are expecting their work to conclude by end of May. After that, we will be able to proceed to the shoring and excavation stages of the process.
Shoring & Excavation
September 1, 2023
Our environmental consultants have been on site doing environmental readings since January 2023. This includes drilling into the ground to take soil samples for a geotechnical and hydrogeological investigations. Their work is just concluding now. After that, we will be able to proceed to the shoring and excavation stages of the process.
| Milestone | Start of Milestone | Status |
| Building Permit Submission | May 2022 | Permit Application Under Review |
| Demolition | November 2022 | Completed |
| Shoring and Excavation | February 2024 | Permit Application Under Review / On schedule |
| Below Grade Forming | June 2024 | Scheduled |
| Above Grade Construction | March 2025 | Scheduled |
| First Occupancy | January 2027 | Scheduled |
Geothermal Preparation & Drilling
December 5, 2023
You may have noticed that work has properly started on the site recently. We have received our geothermal drilling permit, and our geothermal contractors have commenced their investigation and preparation of the site for their equipment. The drilling is not expected to have any vibrational impact on the neighbouring properties, as the boreholes are very small (6” in diameter).
The construction schedule is still the same as in our last updated in September. Please see underneath. We will keep the community up to date with any changes. If you have any questions or feedback, please feel welcome to reach out to us by using the “Contact” form.
| Milestone | Start of Milestone | Status |
| Building Permit Submission | May 2022 | Permit Application Under Review |
| Demolition | November 2022 | Completed |
| Shoring and Excavation | February 2024 | Permit Application Under Review / On schedule |
| Below Grade Forming | June 2024 | Scheduled |
| Above Grade Construction | March 2025 | Scheduled |
| First Occupancy | January 2027 | Scheduled |